Keeping the scope fixed

This project ran on a new kind of delivery: AI agents producing work, people reviewing and steering it. That is a deliberate choice: at Flintbury we are embracing AI-led development. Embracing it changes what a delivery plan has to protect. When agents can produce work faster than people can review it, planning has to adapt around that. This post is about how we planned for it.

The first problem is an old one, though. Agents or not, the ideas never stop.

A baseline worth defending

The challenge with a project like this is keeping the scope fixed. There are never-ending ideas, improvements and special requests, and plenty of them sound reasonable on their own.

The foundation was a formal plan: a feature list, agreed with the client, clearly and concisely, to avoid confusion or frustration later. In industry terms, that agreed list is a scope baseline, and the discipline that keeps it meaningful as changes arrive is change control.

Three steps. Scope baseline: an agreed feature list, agreed with the client clearly and concisely to avoid confusion or frustration later. Ideas keep coming: improvements and requests, plenty of which sound reasonable on their own. Change control: the discipline that keeps the baseline meaningful as changes arrive.
The agreed feature list is the scope baseline; change control keeps it meaningful as ideas arrive.

Sprints with room to breathe

The plan broke the features into sprints, with enough capacity in each one to absorb minor changes without majorly impacting the overall plan. The Scrum Guide talks about planning sprints around the team's capacity; our version of that was leaving room in every sprint for the changes that always come. Small changes are not the enemy. An unbuffered plan is.

Two sprints compared. Without room: a sprint planned to the limit, so a small change has nowhere to go and the overall plan is hit. With room: a sprint with capacity to spare, where the same small change is absorbed and the overall plan holds. Illustrative, not to scale.
Room in every sprint: a small change is absorbed instead of hitting the plan.

One project per component

The work lived in multiple GitLab projects, one per component, and we built our own management tools to track tasks, issues and progress across them. The tracking had to fit the way we worked, not the other way round.

We also chose a simple rule that paid off later: the code keeps track of the features, rather than some outside document. When the time came to catalogue what had actually been built, the catalogue was already there.

The constraint moves

Here is where the new paradigm shows itself. AI agents were part of how we worked, with the GSD AI plug-in alongside them. There is much more to say about that tooling, and it gets its own post next.

What belongs in this post is what the speed did to the humans. Agents running at that pace produce a quantity of issues and merge requests that need human attention, and keeping on top of that was genuinely challenging at first. The Theory of Constraints, a management method built around finding a system's bottleneck, is a useful lens here: when one part of delivery speeds up, the pressure moves elsewhere. For us, it moved to review.

The response was to organise around that pressure. We built a daily email to share progress, and kept daily meetings alongside it. The bespoke tools and the guard rails around the agents let us keep moving without draining our most critical resource: our people.

Flow from agents to people to delivery. Agents produce work: issues and merge requests arrive at a pace people cannot match. Review is where the pressure moves, as every issue and merge request needs human attention. Work then moves forward at a pace the team can sustain. Below, how we organised around review: a daily progress email, daily meetings, and bespoke tools and guard rails.
When agents speed up delivery, the pressure moves to review, so the plan is built around it.

A flow-management lens adds the last piece: issues and merge requests are a flow of work to be managed, not a pile of output to be counted. What the team could review, and move forward, sustainably: that is what the plan had to protect.

A plan is only as good as the team's ability to keep reviewing what the plan produces. Looking back, ours held because the reviewing stayed sustainable. On this project, when agents did the building, everything else in delivery had to be planned around the people who checked the work.

Next in this series: how we built the app with AI. Come back soon to hear how we're progressing as we deliver the platform.